Technical data of the work: primary, secondary and tertiary wastewaters processing, mud treatment, mud thickening and dehydration, decommissioning and demolition of former structures, station testing and maintenance Can serve over 125,800 inhabitants daily Execution duration: 26 months
5000sqm of rehabilitation; execution of stripping, consolidation and architecture – restoration works.
4,438 seats. main competition field, surrounded by grandstands for spectators and a training ground, located in the basement of the building, under the imprint of the main field, both courts having a handball playing area at official dimensions (20x40m), underground
Residential buildings phase 1; Project will continue: up to 1,041 apartments at the end; Built area of around 100,000 square meters. For details: www.arboresidence.ro
the project includes the rehabilitation, modernization and extension of the Tulcea County Emergency Hospital.